Consider the following schedule
S : r1(A) w2(A) commit2, w1(A) w3(A) commit3, commit1
Which of the following is true?
a) Schedule is view serializable schedule and strict recoverable schedule
b) Schedule is non serializable schedule and strict recoverable schedule
c) Schedule is non serializable schedule and not strict recoverable schedule
d)Schedule is serializable schedule and not strict recoverable schedule