619 views

1 Answer

0 votes
0 votes
THIS SCHEDULE IS NOT VALID BECAUSE IN 2 PHASE LOCKING AFTER EXECUTING SHRINKING PHASE NO LOCK OPERATION CAN WE PERFORM ALL LOCK OPERATION PERFORM IN GROWING PHASE.

Related questions

0 votes
0 votes
0 answers
1
gatecrack asked Sep 5, 2018
379 views
Consider th following scheduler1(A)r2(B)r3(C)w1(B)w2(C)w3(D)Find the schedule which are possible to execute by strict 2PL protocol? consider commit operation as immediate...
1 votes
1 votes
1 answer
2
palashbehra5 asked Jan 17, 2022
968 views
Given Problem : S1 can be shown allowed under 2PL.However, the solution that they have provided for S2 : Seems wrong, as So, is S2 allowed under 2PL, or the answer give...
1 votes
1 votes
0 answers
3
0 votes
0 votes
0 answers
4
jayadev asked Jul 2, 2022
347 views
question about concurrency control methods