4 votes 4 votes Which of the following is not a maturity level as per Capability Maturity Model? Initial Measurable Repeatable Optimized IS&Software Engineering is&software-engineering non-gate isro2014 + – kvkumar asked Jun 29, 2016 retagged Nov 13, 2017 by Arjun kvkumar 3.7k views answer comment Share Follow See all 0 reply Please log in or register to add a comment.
Best answer 7 votes 7 votes Answer : Measurable Reference : http://searchsoftwarequality.techtarget.com/definition/Capability-Maturity-Model shekhar chauhan answered Jun 30, 2016 selected Jul 1, 2016 by Arjun shekhar chauhan comment Share Follow See all 0 reply Please log in or register to add a comment.
0 votes 0 votes 5 levels of Capability Maturity Model: Initial Repeatable Defined Managed Optimized Aishwarya Gujrathi answered Apr 12, 2018 Aishwarya Gujrathi comment Share Follow See all 0 reply Please log in or register to add a comment.