select the drawback of waterfall model:

(A) Customer gets opportunity to review the product very late

(B) It does not help the project manager for proper planning

(C) Partial product is built in the initial stages

(D) Poor documentation
 

retagged by

2 Answers

0 votes
0 votes
The main drawback of waterfall model is that the client gets to review the product very late and there is hardly any chance for modifications.. Hence the answer will be (A).

Related questions

2 votes
2 votes
2 answers
1
sh!va asked Sep 21, 2016
541 views
CMM (Capability Maturity Model) is meant for:I. ProcessII. ProductIII. Both I and IIIV. Neither I nor II
1 votes
1 votes
1 answer
2
sh!va asked Jul 9, 2016
496 views
In ...................................... the software functionality is verified against the SRS.(A) System testing(B) Integration testing(C) White box testing(D) Black b...
1 votes
1 votes
1 answer
3
MIRIYALA JEEVAN KUMA asked Jan 21, 2018
679 views
The drawback with stack storage allocation is when the function completes its execution its result cannot be used some point of time later.Can you please explain this bri...
0 votes
0 votes
0 answers
4
gatecse asked Aug 4, 2019
165 views
Software development planning is designed using   activity diagram  object structure diagram activity chart  bar chart