3 votes 3 votes Which of the following is not included in the waterfall model? Requirement analysis Risk analysis Design Coding IS&Software Engineering ugcnetcse-june2016-paper2 waterfall-model + – go_editor asked Aug 16, 2016 • retagged Nov 4, 2017 by Sanjay Sharma go_editor 4.8k views answer comment Share Follow See all 0 reply Please log in or register to add a comment.
Best answer 1 votes 1 votes Waterfall model does not have iteration or feedback path. Requirement Gathering,Design,Coding is there for waterfall model. But no risk analysis. Bcz once done ;we r not doing the iterative action.whatever Done is Done ;).. So Ans is B. Risk Analysis https://en.m.wikipedia.org/wiki/Waterfall_model Rajesh Pradhan answered Aug 16, 2016 • selected Aug 17, 2016 by Sanjay Sharma Rajesh Pradhan comment Share Follow See all 0 reply Please log in or register to add a comment.
0 votes 0 votes Option B. is Correct Answer RAJKUMAR answered Jun 29, 2017 RAJKUMAR comment Share Follow See all 0 reply Please log in or register to add a comment.