Five jobs are waiting to run. Their expected run times are 9,6,3,5,10....which job scheduling technique will result in minimum avg response time.

1) SJF

2) FCFS

3)PRIORITY

4) ROUND ROBIN

1 Answer

0 votes
0 votes
we can't support to RR bcz if time quantum is too large then it work as FCFS..and here time quantum is not given.in this case SJF will give best result.