With the use of SRTF the execution of three processes is as follows, the process A is scheduled first and A has been running for 6 units of time, the process B is arrived process B ran for 2 units of time, later process C is arrived and completed running in 4 units of time. Find the minimum possible burst time of the process A and B.
- 9, 6
- 10, 6
- 12, 8
- 11, 7