What is the view equivalent serial schedule for the following schedule
R2(A); R1(A); W1(C); R3(C); W1(B); R4(B); W3(A); R4(C); W2(D); R2(B); W4(A); W4(B)

  1.   T1 → T2 → T3 → T4.
  2.  T2 → T1 → T3 → T4.
  3.  T1 → T3 → T2 → T4.
  4.  T4 → T2 → T3 → T1.

1 Answer

1 votes
1 votes
Schedule is also a conflict serializable and every conflict serializable schedule is view serializable so sequence will be T1,T2,T3,T4