Please post the solution to solve this time and work problem

2 Answers

1 votes
1 votes
$X + Y$ one day work $= \frac{1}{8}$ $-(i)$

$\frac{X}{2} + 2Y$ one day work $= \frac{1}{5}$

          $X+4Y$ one day work $= \frac{2}{5}$ $-(ii)$

$4 \times (i) - (ii)$

$3X$$= \frac{1}{2} - \frac{2}{5}$

$X$ one day work  $\frac{1}{30}$

Total days taken by $X = \color{Red}{30}$

Related questions

2 votes
2 votes
1 answer
2
Vashishtha asked Mar 16
117 views
If 11th March 1997 was Thursday. What day of the week was on 9th March, 2000 ?
0 votes
0 votes
1 answer
3
Vashishtha asked Sep 9, 2023
438 views
A man wrote all the natural numbers starting from 1 in a series. What will be the 50th digit of the number?a) 1 c) 2b) 3 d) 4
0 votes
0 votes
1 answer
4
vanshikhahere asked Sep 8, 2023
347 views
A starts a business with a capital of 1200. B and C join with investments after 3 and 6 months respectively. If at the end of a year, the profit is divided in the ratio 2...