Answer : (2). (54, 9, 27)
Reason :
We have given with Average Productivity for P = 620 LOC per person-month and we also have 6 Developers.
So Single person can do 620 LOC
Therefore, 6 Developer can do = 6 x 620 = 3720 LOC in a month
Now we need to calculate time T to complete the Project
T = Estimated Line of Code / 6 Developers Line of Code per Month = 33480 / 3720 = 9
Now we need to calculate cost to complete the project in 9 months with given average salary of ₹ 50,000 per month.
Cost = 6 x 9 x 50000 = 27,00,000 (27 Lacs)
So Correct answer is option (2).