Ans is 19.67 

I hope it's understandable..but if any doubts than ask me

0 votes
0 votes
program 1 Program 2 Program 3 
a =2m a =2m a =2m
b=3m b=3m b=3m
c =4m c =4m c =4m
     

Gantt Chart For Program(Completion time )

P1a P1b P1c P2a P2b P2c P2a P2b P2c P2b P3a P3b P3c P3a P3b P3c P3c P2 P1a P2b P2c P2c P P P

0----1-----2----3------4-----5-----6-----7-----8-----9----10----11----12---13----14---15---16--18--21---22---23---24-----27

Program Arrival time  Completion time  Turn Around time  Priority time
1 0 27 27 1 (low )
2 3 25 22 5
3 10 19 9 10(high)
         

 

TAT= (22+9+27)/3=19.33

plz check and correct me if i wrong .. 