Which of the following are the primary objectives of risk monitoring in software project tracking?

P: To assess whether predicted risks do, in fact, occur

Q: To ensure that risk aversion steps defined for the risk are being properly applied

R: To collect information that can be used for future risk analysis

  1. Only P and Q
  2. Only P and R
  3. Only Q and R
  4. All of P, Q, R
edited by

1 Answer

0 votes
0 votes
Risk monitoring is a project tracking activity with three primary objectives:
(1) to assess whether predicted risks occur.
(2) to ensure that risk aversion steps defined for the risk are being properly applied; and
(3) to collect information that can be used for future risk analysis.