Which of the following are the primary objectives of risk monitoring in software project tracking?
P: To assess whether predicted risks do, in fact, occur
Q: To ensure that risk aversion steps defined for the risk are being properly applied
R: To collect information that can be used for future risk analysis
- Only P and Q
- Only P and R
- Only Q and R
- All of P, Q, R