Match $\text{list I}$ with $\text{List II}$
With reference to CMM developed by Software Engineering Institute (SEI)
$\begin{array}{llll} & \text{List I} && \text{List II} \\ (A) & \text{INITIAL} & (I) & \text{Process measurement} \\ (B) & \text{REPEATABLE} & (II) & \text{Process definition} \\ (C) & \text{DEFINED} & (III) & \text{Project management} \\ (D) & \text{MANAGED} & (IV) & \text{ADHOC} \end{array}$
Choose the correct answer from the options given below:
- $A-III, B-IV, C-II, D-I$
- $A-IV, B-III, C-I, D-II$
- $A-IV, B-III, C-II, D-I$
- $A-III, B-IV, C-I, D-II$