A Software project was estimated at $864$ Function Points. A six person team will be assigned to project consisting of a requirement gathering person, one designer, two programmers and two testers. The salary of the designer is $\text{Rs. } 70,000$ per month, requirement gatherer is $\text{Rs. } 50,000$ per month, programmer is $\text{Rs. } 60,000$ per month and a tester is $\text{Rs. } 60,000$ per month. Average productivity for the team is $12$ FP per person month. Which of the following represents the projected cost of the project

  1. $\text{Rs. } 33,20,000$
  2. $\text{Rs. } 43,20,000$
  3. $\text{Rs. } 33,10,000$
  4. $\text{Rs. } 22,10,000$
recategorized by

1 Answer

0 votes
0 votes
one  requirement gathering person salary =50000

one designer           salary =70000

two programmers    salary =2x60000=120 000

 two testers             .salary =2x60000=120 000

Total salary  (of 6 persons )Per month =360 000

Average productivity for the team is 12 FP per person month

Total productivity per month by 6 member team = 72FP

Total project size 864 FP

Duration to complete =864/72=12 months

Total project cost =12x360 000 = 43 20 000  

option B right ans
Answer:

Related questions

0 votes
0 votes
1 answer
1
go_editor asked Nov 20, 2020
1,271 views
Which of the following $UML$ diagrams has a static view?Collaboration diagramUse-Case diagramState chart diagramActivity diagram
0 votes
0 votes
2 answers
2
go_editor asked Nov 20, 2020
1,029 views
Modifying the software by restructuring is calledAdaptive maintenanceCorrective maintenancePerfective maintenancePreventive maintenance