Consider a software project with the following information domain characteristic for calculation of function point metric.
Number of external inputs $(I)=30$
Number of external output$(O)=60$
Number of external inquiries $(E)=23$
Number of files $(F)=08$
Number of external interfaces $(N)=02$
It is given that the complexity weighting factors for $\text{I, O, E, F and N}$ are $\text{4, 5, 4, 10 and 7}$, respectively. It is also given that, out of fourteen value adjustment factors that influence the development effort, four factors are not applicable, each of the other four factors have value $3$, and each of the remaining factors have value $4$. The computed value of function point metric is __________
- $612.06$
- $212.05$
- $305.09$
- $806.9$