An _______ chart is a project schedule representation that presents project plan as a directed graph. The critical path is the __________ sequence of ________ tasks and it defines project ________.

  1. Activity, Shortest, Independent, Cost
  2. Activity, Longest, Dependent, Duration
  3. Activity, Longest, Independent, Duration
  4. Activity, Shortest, Dependent, Duration
edited by

1 Answer

0 votes
0 votes

B. Activity, Longest, Dependent, Duration …

 

CPM (critical path method) models the activities and events of a project as a network….

Activities are identified as nodes and events that signify the start and end of activities are denoted as edges between nodes.

CPM provides a graphical view of the project…

 

It predicts the time required to complete the project.

a. Main aim of CPM is to determine the minimum completion time for a project

b. In CPM, critical path is the longest sequence of dependent tasks and it defines project duration.

c. During forward pass, it is assumed that each activity will begin at its earlies starting time.

d. During backward pass, it is assumed that each activity begins at its latest completion time..

 

Steps of CPM project planning:

1) Specification of individual activities and determining the sequence of those activities.

2) Then draw network diagram as directed graph.

3) Estimation of completion time for each activity.

4) Then identify the critical path or longest path through the network

5) Finally update the CPM as the project progresses…

 

 

Right Answer is: B ...

Related questions

1 votes
1 votes
2 answers
1
4 votes
4 votes
6 answers
3
soujanyareddy13 asked May 12, 2021
1,912 views
The Boolean expression $AB+A \overline{B}+\overline{A}C+AC$ is unaffected by the value of the Boolean variable _________.$A$$B$$C$$A, B$ and $C$