Given $\text{CPU}$ time slice of $2\text{ms}$ and following list of processes.
$$\begin{array}{ccc} \text{Process} & \text{Burst time} & \text{Arrival time} \\ & \text{(ms)} \\ p_1 & 3 & 0 \\ p_2 & 4 & 2 \\ p_3 & 5 & 5 \end{array}$$
Find average turnaround time and average waiting time using round robin $\text{CPU}$ scheduling?
- $4, 0$
- $5.66, 1.66$
- $5.66, 0$
- $7, 2$