Consider a software development project with seven tasks T1-T7.
Activity
|
Duration
|
Dependence
|
T1
|
3
|
-
|
T2
|
2
|
T1
|
T3
|
3
|
T2
|
T4
|
5
|
T1
|
T5
|
2
|
T3,T4
|
T6
|
4
|
T3,T4
|
T7
|
5
|
T3,T4
|
If developer A is available from the start of the project and developer B and C become available after three weeks of the start of the project. Schedule the project and show your results in the form of a bar chart and resource histogram.