Option A: 2,2,4,4. No problem.
Option B: 2,4,2,4. The third job in this sequence had to be completed under 2 time units. But it took 3 time units. This isn't an optimal solution, hence the answer.
Option C: 2,2,4,4. No problem.
Option D: 2,2,4,4. No problem.