8 votes 8 votes On a system using non-preemptive scheduling, processes with expected run times of 5, 18, 9 and 12 are in the ready queue. In what order should they be run to minimize wait time? 5, 12, 9, 18 5, 9, 12, 18 12, 18, 9, 5 9, 12, 18, 5 Operating System isro2007 operating-system process-scheduling + – go_editor asked Jun 10, 2016 • edited Jul 2, 2016 by srestha go_editor 7.8k views answer comment Share Follow See all 0 reply Please log in or register to add a comment.
Best answer 15 votes 15 votes Option B 5 9 12 18 In non preemption Shortest Job First leads to less waiting time shivanisrivarshini answered Jun 10, 2016 • selected Jul 2, 2016 by srestha shivanisrivarshini comment Share Follow See all 0 reply Please log in or register to add a comment.
0 votes 0 votes Option b 5 ,9,12,18 Shortest job first Nbhardwaj answered May 24, 2020 Nbhardwaj comment Share Follow See all 0 reply Please log in or register to add a comment.