Sliding window concept of software project management is:

  1. Preparation of comprehensible plan
  2. Preparation of the various stages of development
  3. Ad-hoc planning
  4. Requirement analysis

1 Answer

Best answer
3 votes
3 votes

Project planning is a very tedious task . If we plan for the complete development process , then especially for the big and risky projects , it is very tough to plan completely 

Hence , we prefer to make plans as the number of stages pass and are successively completed.

As the new stage arrives , we make a seperate plan for it. This technique is called sliding window planning and the project is planned more accurately in successive development stages.

Hence , answer B)

www.nptel.ac.in/courses/106105087/pdf/m11L27.pdf
selected by

Related questions

0 votes
0 votes
2 answers
1
Nils asked Jul 13, 2016
485 views
what is effective line utilization if we increase number of frames for constant message size ?1) become lower efficiency2) become higher efficiency3) No change in eff...
1 votes
1 votes
1 answer
4
gate_forum asked Oct 16, 2015
520 views
amount of time it would take to send 500 packets using 6-packet size window and without sliding window will be, when the time to send in one direction is 5 ms31000, 50004...