Match the following $:$ 

$\begin{array}{clcl}  & \textbf{List – I}&& \textbf{List – II} \\ \text{a.} & \text{Correctness}& \text{i.} & \text{The extent to which a software tolerates} \\ &&& \text{the unexpected problems.} \\  \text{b.} & \text{Accuracy}& \text{ii.} & \text{The extent to which a software meets its} \\ &&& \text{specification} \\ \text{c.} & \text{Robustness}& \text{iii.} & \text{The extent to which a software has the} \\ &&& \text{specified functions} \\ \text{d.} & \text{Completeness}& \text{iv.} & \text{Meeting specifications with precision}  \\  \end{array}$

$\textbf{Codes :}$

  1. $\text{a-ii, b-iv, c-i, d-iii}$
  2. $\text{a-i, b-ii, c-iii, d-iv}$
  3. $\text{a-ii, b-i, c-iv, d-iii}$
  4. $\text{a-iv, b-ii, c-i, d-iii}$
edited by

2 Answers

Best answer
5 votes
5 votes

Answer : A

LIST-1                               LIST-II
a. Correctness           ii. The extent to which a software meets its specifications 
b. Accuracy               iv. Meeting specifications with precision
c. Robustness           i. The extent to which a software tolerates the unexpected problems
d. Completeness       iii. The extent to which a software has specified functions

Reference : What is Correctness?   Accuracy  Robustness   Completeness       

         

selected by
0 votes
0 votes

Answer A

* Correctness : working as per requirements => ii

Accuracy : how much precisely answer is coMputed => iv

* robustness : how much error software can tolerate and avoid crashing=> i

**completeness :  how much requirements the software is meeting => iii

Answer:

Related questions

0 votes
0 votes
2 answers
3
makhdoom ghaya asked Jul 9, 2016
2,902 views
Which one of the following is not a key process area in CMM level $5$ ?Defect preventionProcess change managementSoftware product engineeringTechnology change management