Match the following $:$

$\begin{array}{}  \text{a. }& \text{Watson-Felix model} & \text{i.}& \text{Failure intensity} \\ \text{b.}& \text{Ouick-Fix model} & \text{ii.} & \text{Cost estimation} \\ \text{c.} & \text{Putnam resouce allocation model} & \text{iii.} & \text{Project planning} \\ \text{d.} & \text{Logarithmetic Poission Model}&  \text{iv.} & \text{Maintainace} \\ \end{array}$

$\textbf{Codes :}$

  1. $\text{a-ii, b-i, c-iv, d-iii}$
  2. $\text{a-i, b-ii, c-iv, d-iii}$
  3. $\text{a-ii, b-i, c-iii, d-iv}$
  4. $\text{a-ii, b-iv, c-iii, d-i}$
edited by

1 Answer

0 votes
0 votes

Ans: D

a. Watson-Felix model is a cost estimation model similar to cost estimation model which says Effort, E= 5.2 (KLOC) 0.91

b Quick fix model: A software maintenance approach in which we wait till problem occurs and fix it as quickly as possible

c. Putnam resource allocation model is used for effort estimation for a project and is used while planning a project. This model gives the famous relation effort α 1/time 4

d. Logarithmic Poisson Execution Time Model for Software Reliability Measurement

 

 