The number of function points of a proposed system is calculated as 500. Suppose that the system is planned to be developed in Java and the LOC/FP ratio of Jave is 50. Estimate teh effort (E) required to complete the project using the effort formula of basic COCOMO given: E=a(KLOC)$^b$
Assume that the values of a and b are 2.5 and 1.0 respectively
- 25 person months
- 75 person months
- 62.5 person months