The number of function points of a proposed system is calculated as 500. Suppose that the system is planned to be developed in Java and the LOC/FP ratio of Jave is 50. Estimate teh effort (E) required to complete the project using the effort formula of basic COCOMO given: E=a(KLOC)$^b$

Assume that the values of a and b are 2.5 and 1.0 respectively

  1. 25 person months
  2. 75 person months
  3. 62.5 person months
  4. 72.5 person months