0 votes 0 votes 'A' can complete a piece of work in 12 days. 'A' and 'B' together can complete the same piece of work in 8 days. In how many days can 'B' alone complete the same piece of work? Quantitative Aptitude go-general-aptitude-1 quantitative-aptitude numerical-answers + – Bikram asked Sep 28, 2016 Bikram 239 views answer comment Share Follow See all 0 reply Please log in or register to add a comment.
2 votes 2 votes A can do 1/12 th of work in one day let x be the number of days by B to do the work alone therefore 1/12 + 1/x = 1/8 simplifying x = 24 Sankaranarayanan P.N answered Sep 29, 2016 Sankaranarayanan P.N comment Share Follow See all 0 reply Please log in or register to add a comment.