<Q>.Manoj takes twice as much time as Ajay and thrice as much as Vijay to finish a piece of work .Together they finish the work in 1 day.What is the time taken by Manoj to finish the work?

  <a>.6 days             <b>.3 days

  <c>.2 days             <d>.none

1 Answer

1 votes
1 votes
Manoj takes twice as much time as Ajay and thrice as much as Vijay

Manoj takes x days ,Ajay takes x / 2  days and vijay takes x / 3  days

together they work then finished in 1 day

1 / x + 2 / x + 3 / x = 1

6 / x = 1  

x = 6

So, manoj takes 6 days to complete work.

Related questions

1 votes
1 votes
4 answers
3
Sangay asked Aug 5, 2018
1,044 views
A can do piece of work in 30 days while Bonku alone can do it in 40 days. If they work together, how long will it take to complete the work?
0 votes
0 votes
3 answers
4
Manikant Kumar asked Sep 16, 2016
1,041 views
6. A team P of 20 engineers can complete work or task in 32 days. Another team Q of 16 engineers can complete same task in 30 days.Then the ratio of working capacity of 1...