4 votes 4 votes Draw the space time diagram for a 6-segment pipeline showing the time it takes to process 8 no of tasks.Determine the no of clock cycle that it takes to process 200 tasks. CO and Architecture co-and-architecture + – rahuldb asked Nov 17, 2016 • retagged Nov 13, 2017 by Arjun rahuldb 18.8k views answer comment Share Follow See all 0 reply Please log in or register to add a comment.
Best answer 5 votes 5 votes 1st task would need 6 clock cycles to come out of pipeline and then remaining 7 tasks would need 1 clock cycle each = total 13 clock cycles. So 200 tasks would need = 6+199 clock cycles = 205 clock cycles. Amitabh Tiwari 1 answered Nov 18, 2016 • edited May 13, 2021 by Arjun Amitabh Tiwari 1 comment Share Follow See 1 comment See all 1 1 comment reply whoami_shubham commented May 9, 2018 i reshown by whoami_shubham May 9, 2018 reply Follow Share in case of 200 task why answer would not be 6 + 199 i.e 205 clock cycle instead of 399 clocks 0 votes 0 votes Please log in or register to add a comment.