GATE IT 2006 | Question: 83
A software project has four phases P1, P2, P3 and P4. Of these phases, P1 Is the first one and needs to be completed before any other phase can commence. Phases P2 and P3 can be executed in parallel. Phase P4 cannot commence until both P2 and P3 ... be spent on crashing so that ALL paths are critical are, respectively. 100 and 1000 100 and 1200 150 and 1200 200 and 2000
A software project has four phases P1, P2, P3 and P4. Of these phases, P1 Is the first one and needs to be completed before any other phase can commence. Phases P2 and P3...
Ishrat Jahan
1.7k
views
Ishrat Jahan
asked
Nov 1, 2014
IS&Software Engineering
gateit-2006
is&software-engineering
project-cost
normal
non-gate
+
–
6
votes
1
answer
2
GATE CSE 2011 | Question: 5, ISRO2016-64
A company needs to develop a strategy for software product development for which it has a choice of two programming languages L1 and L2. The number lines of code (LOC) developed using L2 is estimated to be twice of the LOC developed with L1. The ... which of the cost of the project using L1 is equal to the cost of the project using L2? 4000 5000 4333 4667
A company needs to develop a strategy for software product development for which it has a choice of two programming languages L1 and L2. The number lines of code (LOC) de...
go_editor
7.7k
views
go_editor
asked
Sep 29, 2014
IS&Software Engineering
gatecse-2011
is&software-engineering
project-cost
normal
isro2016
+
–