Recent questions tagged risk-management
2
votes
1
answer
1
UGC NET CSE | December 2014 | Part 3 | Question: 45
Assume that the software team defines a project risk with $80$% probability of occurrence of risk in the following manner: Only $70$ percent of the software components scheduled for reuse will be integrated into the application and the remaining functionality ... $25,200 $20,160 $17,640 $15,120
Assume that the software team defines a project risk with $80$% probability of occurrence of risk in the following manner: Only $70$ percent of the software components sc...
makhdoom ghaya
8.5k
views
makhdoom ghaya
asked
Jul 29, 2016
IS&Software Engineering
ugcnetcse-dec2014-paper3
is&software-engineering
risk-management
+
–
1
votes
1
answer
2
UGC NET CSE | September 2013 | Part 3 | Question: 50
Sixty reusable components were available for an application. If only 70% of these components can be used, rest 30% would have to be developed from scratch. If average component is 100 LOC and cost of each LOC is Rs. 14, what will be risk of exposure if risk probability is 80%? Rs. 25, 200 Rs. 20, 160 Rs. 25, 160 Rs. 20, 400
Sixty reusable components were available for an application. If only 70% of these components can be used, rest 30% would have to be developed from scratch. If average com...
go_editor
2.7k
views
go_editor
asked
Jul 24, 2016
IS&Software Engineering
ugcnetcse-sep2013-paper3
is&software-engineering
risk-management
+
–
0
votes
1
answer
3
UGC NET CSE | June 2014 | Part 2 | Question: 12
Which one of the following is not a risk management technique for managing the risk due to unrealistic schedules and budgets ? Detailed multi source cost and schedule estimation. Design cost Incremental development Information hiding
Which one of the following is not a risk management technique for managing the risk due to unrealistic schedules and budgets ?Detailed multi source cost and schedule esti...
makhdoom ghaya
4.4k
views
makhdoom ghaya
asked
Jun 25, 2016
IS&Software Engineering
ugcnetcse-june2014-paper2
is&software-engineering
risk-management
+
–