i.) Peak Manning can be calculated by – Project effort in PY (K) / dev time(in yrs) * √e,   √e = 1.648, dev time = 3 yr 6 months = 3.5 yrs

= 600/(3.5 * 1.648) =      104.022 =104 persons
Peak time can be calculated by – Dev time in years/√6 
= 3.5/√6 = 1.42 yrs