Consider the basic COCOMO model where $E$ is the effort applied in person-months, $D$ is the development time in chronological months, $KLOC$ is the estimated number of delivered lines of code (in thousands) and $a_b, b_b, c_b, d_b$ have their useful meanings. The basic COCOMO equations are of the form

  1. $E=a_b (KLOC) exp(b_b), D=c_b(E) exp(d_b)$
  2. $D=a_b (KLOC) exp(b_b), E=c_b(D) exp(d_b)$
  3. $E=a_b exp(b_b), D=c_b (KLOC) exp(d_b)$
  4. $E=a_b exp(d_b), D=c_b (KLOC) exp(b_b)$

3 Answers

Best answer
4 4 votes

Answer: A

In basic COCOMO model,

Effort Applied, E = a*(KLOC)b
Development Time, D = c*Ed
People Required, P = E/D

where KLOC = Estimated number of delivered lines in thousands and a,b,c,d depends upon the software being Organic, Semi detached or Embedded.

http://www.mhhe.com/engcs/compsci/pressman/information/olc/COCOMO.html

• selected by
0 0 votes

COCOMO Model stands for Constructive Cost Estimation Model widely used in software engineering. 

If E is the effort applied in person-months, D is the development time in chronological months, KLOC is the estimated number of delivered lines of code (in thousands) and ab,bb,cb,db have their useful meanings. The basic COCOMO equations are of the form

E =ab(KLOC)exp(bb), D=cb(E)exp(db)

Answer:
Position:
Show:

Related questions

4 4 votes
1 answers 1 answer
3.9k
3.9k views
go_editor asked Feb 12, 2015
3,874 views
Which one of the following assertions concerning code inspection and code walkthrough is true?Code inspection is carried out once the code has been unit testedCode inspec...
5 5 votes
1 answers 1 answer
9.7k
9.7k views
go_editor asked Feb 12, 2015
9,704 views
A software requirements specification (SRS) document should avoid discussing which one of the following?User interface issuesNon-functional requirementsDesign specificati...
4 4 votes
1 answers 1 answer
7.6k
7.6k views
go_editor asked Sep 29, 2014
7,608 views
A company needs to develop a digital signal processing software for one of its newest inventions. The software is expected to have 40000 lines of code. The company needs ...
1 1 vote
1 answers 1 answer
4.7k
4.7k views
Ishrat Jahan asked Nov 1, 2014
4,700 views
In a software project, COCOMO (Constructive Cost Model) is used to estimateeffort and duration based on the size of the softwaresize and duration based on the effort of t...