A company needs to develop a strategy for software product development for which it has a choice of two programming languages L1 and L2. The number lines of code (LOC) developed using L2 is estimated to be twice of the LOC developed with L1. The product will have to be maintained for five years. Various parameters for the company are given in the table below.

ParameterLanguage L1Language L2
Man years needed for developmentLOC/10000LOC/10000
Development Cost per man yearर 10, 00, 000 7, 50, 000
Maintenance Time5 years5 years
Cost of maintenance per year 1,00,000 50, 000

Total cost of the project includes cost of development and maintenance. What is the LOC for L1 for which of the cost of the project using L1 is equal to the cost of the project using L2?

  1. 4000
  2. 5000
  3. 4333
  4. 4667

1 Answer

Best answer
14 14 votes
Answer: B

Let L1 = x and L2 = 2x

Then, (x*1000000)/10000 + 5*100000 = (2x*750000)/10000 + 5*50000
=> x*100 + 5*100000 = 2x*75 + 5*50000
=> 50x = 250000
=> x = 5000
Answer:
Position:
Show:

Related questions

8 8 votes
1 answers 1 answer
7.4k
7.4k views
sh!va asked May 7, 2017
7,379 views
Estimation at software development effort for organic software in basic COCOMO is:E = 2.0 (KLOC) 1.05 PME = 3.4 (KLOC) 1.06 PME = 2.4 (KLOC) 1.05 PME = 2.4 (KLOC) 1.07...
74 74 votes
4 answers 4 answers
24.1k
24.1k views
go_editor asked Sep 29, 2014
24,115 views
On a non-pipelined sequential processor, a program segment, which is the part of the interrupt service routine, is given to transfer $500$ bytes from an I/O device to mem...
2 2 votes
3 answers 3 answers
2.6k
2.6k views
Ishrat Jahan asked Nov 1, 2014
2,589 views
A software project has four phases P1, P2, P3 and P4. Of these phases, P1 Is the first one and needs to be completed before any other phase can commence. Phases P2 and P3...
7 7 votes
2 answers 2 answers
7.3k
7.3k views
Ishrat Jahan asked Oct 29, 2014
7,286 views
In the Spiral model of software development, the primary determinant in selecting activities in each iteration isIteration sizeCostAdopted process such as Rational Unifie...