A company needs to develop a digital signal processing software for one of its newest inventions. The software is expected to have 40000 lines of code. The company needs to determine the effort in person-months needed to develop this software using the basic COCOMO model. The multiplicative factor for this model is given as 2.8 for the software development on embedded systems, while the exponentiation factor is given as 1.20. What is the estimated effort in person-months?

  1. 234.25
  2. 932.50
  3. 287.80
  4. 122.40

1 Answer

Best answer
9 9 votes

kLOC = 40000/1000 = 40

Effort Applied (E) = 2.8(40)^1.2 [ person-months ]

                            = 234.22

• selected by
Answer:
Position:
Show:

Related questions

4 4 votes
1 answers 1 answer
4.4k
4.4k views
go_editor asked Sep 29, 2014
4,445 views
The following is the comment written for a C function./* This function computes the roots of a quadratic equation a.x^2 + b.x + c = 0. The function stores two real roots ...
9 9 votes
5 answers 5 answers
9.0k
9.0k views
go_editor asked Sep 28, 2014
8,970 views
In the context of modular software design, which one of the following combinations is desirable?High cohesion and high couplingHigh cohesion and low couplingLow cohesion ...
76 76 votes
4 answers 4 answers
24.7k
24.7k views
go_editor asked Sep 29, 2014
24,717 views
On a non-pipelined sequential processor, a program segment, which is the part of the interrupt service routine, is given to transfer $500$ bytes from an I/O device to mem...
4 4 votes
3 answers 3 answers
5.3k
5.3k views
go_editor asked Feb 12, 2015
5,288 views
Consider the basic COCOMO model where $E$ is the effort applied in person-months, $D$ is the development time in chronological months, $KLOC$ is the estimated number of d...