Project schedular
Consider a software development project with seven tasks T1-T7. Activity Duration Dependence T1 3 - T2 2 T1 T3 3 T2 T4 5 T1 T5 2 T3,T4 T6 4 T3,T4 T7 5 T3,T4 If developer A is available from the start of the project and developer B and C ... after three weeks of the start of the project. Schedule the project and show your results in the form of a bar chart and resource histogram.
Consider a software development project with seven tasks T1-T7.ActivityDurationDependenceT13-T22T1T33T2T45T1T52T3,T4T64T3,T4T75T3,T4 If developer A is available from the ...
421
views
asked
Jan 1, 2023
IS&Software Engineering
is&software-engineering
software-development-life-cycle-models
+
–
Email or Username
Show
Hide
Password
I forgot my password
Remember
Log in
Register