allocated Max need
P1 6 11 5
P2 3 5 2 total resource =13 AND free resources =13-11=2 so clearly these 2 can only be given
P3 2 8 6 to P2 which will be completed and release its all 5 resource then next P1 can take 5 resource and be completed and finally P3
so right ans is choice 1 P2P1P3