3 3 votes Consider a scenario where 3 processes P1, P2 and P3 are sharing X resources of the same type. The maximum need of the three processes is 4, 8, 6. It is also known that the maximum combined need of both processes P1 and P2 at a time is 9 and they always execute only in a combined manner. Then the value of X+ 7 is ________. Operating System + – tapzo 662 views answer comment Share Follow Print See all 2 Comments 2 2 Comments reply Anu007 commented Jan 12, 2018 reply Follow flag 21.... 1 1 replyShare tapzo commented Jan 12, 2018 reply Follow flag plz explain yes you are right 0 0 replyShare Please log in or register to add a comment.
0 0 votes here we have to select a number randomly given p1 requires 4 p2 requires 8 p3 requires 6 p1+p2 both require minimum 9 resources at same time so let us assume x=10 process allocated required p1 3 1 p2 6 2 p3 1 5 so it may lead to unsafe state now let us assume x=12 if we create a resource allocation table then the system will be always in safe state so x=12 and x+7=19 Deepthi_ts answered Jan 12, 2018 Deepthi_ts comment Share Follow 0 reply Please log in or register to add a comment.