1 1 vote A system has 10 identical resources and N processes competing for them. Each process can request atmost 3 resources but by grouping of first 3 processes needs only 6 resources. Then, the maximum value of ‘N’ is _______ Operating System + – khedkar devidas 516 views answer comment Share Follow Print See all 2 Comments 2 2 Comments reply sandeep007734 commented Jan 29, 2018 reply Follow flag First three process takes 6 resources. As there is no other options are given, assuming the next process asks for 3 resources, then the total requirement is 9. However, as the questions is asking for max values of N, then we have to assume that all the new process takes the minimum amount of resource, which is 1 and hence total new process that can be accommodated is 4, which takes the total number of processes to 3 + 4 = 7. Hence N = 7. 0 0 replyShare khedkar devidas commented Jan 29, 2018 reply Follow flag Ans given was 6 0 0 replyShare Please log in or register to add a comment.