0 0 votes If a software project has $2000$ lines of code (LOC) and the average productivity rate is $10$ LOC per person-hour, how many person-hours are required to complete the project?$100$$150$$200$$250$ IS&Software Engineering ugcnetcse-aug2024 is&software-engineering quantitative-aptitude + – Shubham Sharma 2 294 views answer comment Share Follow Print 0 reply Please log in or register to add a comment.
1 1 vote Total Line of code / productivity rate per hour = number of hours required~ 200 hours [ Option B ] vxi lin answered Nov 18, 2025 vxi lin comment Share Follow 0 reply Please log in or register to add a comment.